Wellness Center
Physicians’
Clinic
Replacement Hospital Bond Issue Proposal
Hospital Main
Entrance
Phased Masterplan
 PHASE 1 – 67,213sf
 PHASE 3 – 118,122sf
 PHASE 5 – 13,223sf
Total
198,558sf
Existing Medical Center
134,400 sf
 Original Built in 1962
 Original built for 110 beds
 Hospital 109,000sf, Doctor’s Clinic 25,400sf
 12 acre campus
Permian Regional Medical Center
PHASE 1
67,213 sf
 Wellness Center
 Physician’s Clinic
 Physical Therapy
Permian Regional Medical Center
PHASE 2
 Demolition of Doctor’s Clinic/Storage Building
 Relocate gas/electrical in NE Hospital Drive
 Close/demolish portion NE Hospital Drive
Permian Regional Medical Center
PHASE 3
118,122 sf
 New Main Hospital construction
 New Central Energy Plant construction
 Connect Phase 1 Buildings to new CEP
Permian Regional Medical Center
PHASE 4
 Demolition of 3-story hospital
 Demolition of existing Central Energy Plant
 Demolish original hospital parking/drive
Permian Regional Medical Center
PHASE 5
13,223 sf
 Construction of Dining/Employee Services
 Connect permanently to Skilled Nursing Facility
 Connect to Central Energy Plant
Permian Regional Medical Center
Departmental Masterplan
Summary Timeline
Permian Regional Medical Center
2012
2014
2013
6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12
Phase 1 - Physician’s Clinic/Wellness
Design
6 mos
2015
1 2 3 4 5 6 7 8 9 10 11 12
2016
1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6
Move In
1 mo.
Construction
12 mos
Demo
2 mo.s
Phase 2 – Demolition
Phase 3 – Hospital/Central Plant
Design
8 mos
Construction
15 mos
Move In
1 mo.
Demo
3 mo.s
Phase 4 – Demolition
Phase 5 - Dining/Connection
Design
4 mos
6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12
Construction
5 mos
1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
Move In
1 mo.s
1 2 3 4 5 6
Project Cost Summary
Permian Regional Medical Center
Building Construction
•
•
•
•
•
•
General Construction (198,588 sf)
Demolition
Site Work
Streetwork
Infrastructure
Landscaping
Other Costs
•
•
•
•
•
•
•
Bond Counsel Fees
Design Fees (architecture, engineering)
Printing Costs etc.
Testing
State Reviews and Inspections
Real Estate acquisition
PRMC Move-in expenses
Construction Total
$ 59,305,087
Interiors
Permian Regional Medical Center
Wellness Area
Public Mall
Wellness Center
Hospital Entry Plaza
Design & Graphics by Bundy, Young, Sims & Potter,
Inc./Trinity Hughes, 2011
Hospital Main
Entrance